Work experience 17 years 4 months
November 2013 — April 2015
1 year 6 months
Silangan Mindanao Mining Company Incorporated
Mining Industry... Show more
Superintendent
Mechanical Maintenance and Engineering Department
Silangan Mindanao Mining Company Incorporated
* Provides the leadership, direction and control over all surface and underground equipment repair and maintenance related mechanical services.
* Directly responsible in the repair, maintenance and installation of equipment and other related machinery such as:
- Mobile Plant:
* Dump truck, Excavator, Road grader, dozer, Compactor. Light vehicle ;
* Load haul dumps(LHD),Low profiles(LPT),Jumbo Drills ;
* Shotcrete , mixers and scaler
- Fixed Plant:
* Batching plant and related loading/unloading facilities.
* Mine Dewatering Pumps, Pneumatic drills, drilling accessories
* Dewatering Piping and equipment set up and installation.
* Generator /power plant
* cement mixers and concrete placers
* Monitoring and control of mine air supply and fabrication / installation of Ventilation facilities such as:
- Shaft sink axial fans ;
- Installation of Electric driven compressors and its pipe line and accessories.
- Layout and installation air pipe line and vent tubes.
- Maintenance/reconditioning of fans, blowers and compressors.
* Implement and enforce all safety, health and environmental standards, policies and rules and regulations.
* Prepares and implements preventive maintenance schedule on all underground and surface equipment installations and other related equipment.
* Prepares, endorse and implement all approved continuous improvement and cost cutting programs.
* Responsible for the Planning, forecasting and ordering of logistical requirement of all equipment, machinery and all their related installations consistent to the approved budget.
* Prepare and endorse to the Maintenance Manager annual budget and CAPEX requirement.
* Prepare monthly reports over all equipment, projects and other related activities under his area of responsibility.
* Responsible for the implementation/monitoring and control of approved budget applicable to his area of responsibility.
* Implement and enforces all company personnel policies and rules and regulations.
* Recommend and implement all approved manpower training and skill improvement.
* Coordinate with all other groups/department in carrying out his duties and responsibilities.
* Performs other related functions that the Maintenance Manager may assign from time to time.
October 2011 — October 2013
2 years 1 month
Samsung Engineering
Piping Supervisor
SAMCO ``AA'' Project
Jubail Industrial City
Shaybah Inlet Gas Treatment Project
Shaybah-Package 1
* Perform concurrent function as Piping-Lead Supervisor. ;
* Responsible in leading and directing the team of supervisors in piping construction.
* Coordination with subcontractor regarding to their daily activities
* Attend meetings and advise Subcontractor the priorities to be taken into consideration.
* Attend Internal meeting with other Discipline (if required) for matters to be clarified
* Monitor work progress in accordance with their submitted work schedule
* Explain to Subcontractor their responsibilities and Scope of Work that matters to
their extent of Work if conflict arises.
* Review and interpret construction and engineering drawings and specifications, And
Check the implementation on site.
* Prepare and answer technical queries associated with any piping aspect of the work, as per
Sabic standard.
* Monitor Equipment/Materials availability to attain as per work schedule.
* Keep daily activity progress record and log any problems that may exist, And take
immediate action.
* Perform routine observation reports, to ensure safety practices always carried out on site.
* Inform Group leader about any technical problems that may arise at site to avoid delay.
* Prepare daily reports of work progress and man power utilization.
* Prepare weekly reports of the total spool erection, isometric weight installed, welded
dia. inches of supports and joints and the remaining work front with the materials available.
* Co-ordinate with the subcontractors to achieve the target schedule set by the planning.
* Issue the work permits ensuring SHE requirements. ;
* Conduct safety walk through in the site in co-ordination with the safety department.
* Supervision of all piping works and ensures safety and quality standards of the client.
* Inspection and approval of all the QA/QC submittals of the subcontractor.
* Punch clearing on construction and system punch.
May 2010 — May 2011
1 year 1 month
Nakilat Ship Repair Yard
Piping Supervisor Daewoo Engineering & Construction
Ras Laffan Port / Qatar Petrolium
Al-khor, State of Qatar
* Supervision, execution of fabrication and erection of ship repair yard piping system.
* Direct and control manpower, site work assignment and manpower distribution.
* Review plan and isometric drawings for work shop fabrication and site installation.
* Prepare construction drawings and the take off of materials needed in the site installation
* Give directives to the Material controller for the preparation and delivery of materials as per daily work plan, to avoid delay and met the target schedule.
* Perform routine inspection, monitoring and update of actual work status and evaluate any abnormalities to insure continuing compliance on the client requirement.
* Assessments of manpower, tolls and equipment supply to met the work load and schedules.
* Review daily bonding reports as per joint and dia. Inch.
* Make daily report and one day look ahead schedule. ;
* Enhance safety to the people and plant equipments and facilities, to apply
HSE principles across all projects technical activities.
December 2008 — September 2009
10 months
Jicon International Co. W.l.l
Mechanical Engineer
Ras Laffan Refinery / Qatar Gas
* Reporting to the Mechanical Manager Assign and have direct supervision in the development of mechanical fabrication, installation and punch clearing and commissioning works.
* Make work plan, manpower and equipment distribution and scheduling
* Assessments of manpower, tolls, equipment and material supply to meet the requirements on work load and schedules.
* Make actual material take off, ordering and forecast the procurement to ensure the availability on site as per work schedules.
* Site monitoring and update/audit to ensure that the ongoing installation and commissioning works are carried out to comply as per company requirements.
* Attain daily coordination meeting with the contractors, sub-contractors and the company representative to make action on the discrepancy and abnormalities of the project to meet the contract requirements.
* Enhance to apply HSE principles across all projects technical activities safety to the people, plant equipments and facilities,
* Monitor and assist the third party (contractor) in executing of the testing and inspection.
August 2005 — September 2007
2 years 2 months
Thermo LLC
Site Engineer
Dubai International Airport Expansion
Dubai, U.A.E.
September 2004 — March 2005
7 months
Hinatuan Mining Corporation
Project Engineer
Mining / Exploration Project
Nonoc Is. Surigao City
* Directs and lead the group in the drilling operations. ;
* Forecast and ordering of consumable materials use in the operation.
* Prepare daily work schedule and drilling equipment assignments.
* Advice the survey personnel to established the staking and tagging of
Drilled holes number for the areas to be drill.
* Coordinate to the mobile and mining equipment for:
- The preparation of access roads. ;
- Transferring of drilling equipment and accessories. ;
- Water truck delivery and core samples to Assay laboratory.
* Make daily reports, for the number of drilled holes. Meters deep drilled and classification of core samples extracted.
* Enhance safety precautions on and off the project site works.
September 2002 — March 2004
1 year 7 months
DAI DAN PHILIPPINES INC.
Assistant Mechanical Engineer
Mindanao Container Terminal ( MCTP )
Mitsubishi, Kawasaki, Toyo, Joint Venture (MKTJV)
Tagoloan, Cagayan de Oro city
* Supervision and execution of the mechanical installation works :
- Fire Protection system
- Sanitary and Plumbing system.
- Control Tower stair pressurization / Ventilation System.
* Review and make shop drawing installation details for the clients approval.
* Make the inventory of in house materials, forecast & follow up the procurement to ensure the availability on site as per work schedules.
* Monitoring and checking of materials used and the actual work status in accordance with the tender documents to ensure continuing compliance on the contract requirement.
* Recommends necessary action and solutions needed in the installation as per actual site conditions.
* Follow-up the sub contractors of their manpower, materials and equipment supply, to maintain satisfactory work progress to met the target due date.
* Enhance safety pre-cautions on and off the project site works.
* Attend kick-off meetings and coordination to other services in areas of discrepancy for which corrective action are required.
* Update as built shop drawings, as per actual layout & installed.
* Provide test and inspection request, fully coordinated with the client.
* Performs inspection and functional test to determine the quality of work and materials conform to specification requirements.
* Provide documentation of the results of all inspections and test required by the contract documents.
* Make weekly and monthly reports.
June 1997 — July 2001
4 years 2 months
Manila Mining Corp.
Mechanical Design Engineer
* Take a routine inspection of plant machinery and its components, And make reports recommendation for servicing or replacement and repair.
* Take records and trouble shooting the cause of downtime, and recommends necessary action to eliminate the recurrence of the problem for further upgrade and improve the system.
* Conduct physical inspection and testing of newly replace equipment parts and parts, to pass the standard specification and requirements.
* Performs functional test and commissioning.
* In charge in the mechanical designs, calculation and cost estimates of expansion projects and revised plant set up.
* Make evaluation and recommendation of any changes of the machinery set up, as per upgrading the production.
* Compilation of all the data's of the equipment and its components for reference and ordering purposes..
* support crew of all major shutdowns and repair. ;
* Perform a concurrent function as Copper Flotation Superintendent
November 1996 — May 1997
7 months
Manila Mining Corp.
Preventive Maintenance Inspector
• Take a routine inspection of plant machinery and its components, And make reports recommendation for servicing or replacement and repair.
• Take records and trouble shooting the cause of downtime, and recommends necessary action to eliminate the recurrence of the problem for further upgrade and improve the system.
• Conduct physical inspection and testing of newly replace equipment parts and parts, to pass the standard specification and requirements.
• Performs functional test and commissioning
June 1995 — November 1996
1 year 6 months
Manila Mining Corp.
Supervisor
10,000 TPD / Mill Plant Expansion
* In charge in the Supervision and execution of mechanical installation works:
- Mill structures, Crushing, Conveying, milling machinery and pumping system such as:
- Jaw crusher, Vibrating screen, Conveyors, Chutes, Apron feeders
- Sag Mills, CIP/CIL tanks and agitators ;
- Cyclones, Pumps , valves and pipeline installation. ;
- Re-conditioning of equipment and its accessories. ;
- Preparation of necessary required fabricated tools and equipment.
* Review the detailed working drawing and perspective. ;
* Make actual material take off, ordering and forecast the procurement to ensure the availability on site as per work schedules.
* Proposed possible solution for the discrepancy and conflict in the installation.
* Review all the progress billing of the sub contractors if it conforms against the actual progress of the installation on site.
* Enhance safety pre cautions on and off the project site works.
* Performs inspection functional test.
February 1994 — May 1995
1 year 4 months
Steel Pro
Supervisor
Bo. Osorio, Tanza, Cavite
* Overall in charge in the supervision and execution of the fabrication and construction of 120 M X 42 m ware house.
* Prepare work program and manpower scheduling. ;
* Expedition and preparation of materials, tools & equipment needed.
* Review plans and drawings and Check the fabrication and assembling of Structural members as per given fabrication drawings.
* Perform routine inspection, monitoring and update of actual work status and evaluate any abnormalities to insure continuing compliance on the contract requirement.
* Imposed safety measures in the installation and erection of Steel Structures.
* Coordination with the clients for any abnormalities and changes made in the fabrication and erection.
* Make weekly progress report and prepare progress billing.
Control Room Operator July 31, 1993 - Jan. 22, 1994
About me
Forecasting, Mechanical Installation, Fire Protection, personnel policies, manpower scheduling, direct supervision, Wide experience, Supervision of actual layout and installation, Responsible for the Planning, Procurement, Plumbing, Planned Maintenance, Petrochemicals, P&ID, Mobile Plant, Joint Venture, Generators, General Arrangement Drawings, Excavators, Dumper Trucks, Continuous Improvement, Capital Expenditures
Higher education (bachelor)
1988
Higher education (bachelor)
University of the Visayas
Engineering and construction, Education in Natural Sciences
Languages
Citizenship, travel time to work
Citizenship: Philippines, Russia
Permission to work: Russia