Work experience 21 year 7 months
September 2013 — currently
12 years 8 months
Foster Wheeler
Russia
Mining Industry... Show more
Snr. PE
2020 - now. Currently located in Krasnoyarsk. Bank Feasibility Study for gold mine development Sukhoi Log. Role: calendar and resource planning (for an engineering subcontractor scope) , schedule control (weekly meetings, actions, follow-up), progress control (by means of meetings with discipline leads), scope change control, engineering change control, interface with subcontractor.
2019 - 2020. Pre-Feasibility Study for copper/nickel deposit development on Novaya-Zemlya Archipelago. Role: Recognition site survey.
2018-2019 Fabrication and supply of fired oil heaters to Slavyansk refinery. Role: Project controls of design, fabrication and installation of heaters.
2016-2018 Potash Plant for Eurochem(FEED, DD); my role - development of contractor's schedules in P6, progress controls&reporting, schedule control (schedule control meetings, risks, mitigations).
2013 - 2016: LNG plant on Sakhalin. Project Engineer for pre-FEED, FEED and Declaration (petition) of Intent for a new LNG plant at Sakhalin. Marine faciliities, Pipeline and LNG plant.
Particularly regarding Planning: Compilation of contractor schedules to ensure consistency with Project master-schedule, schedule&progress control, reporting.
Separately from above - development of a methodology for management and schedule optimization of Basic Design - FEED - PROYEKT package development.
Also a few minor brownfield projects in Angarsk, Perm.
January 2011 — September 2013
2 years 9 months
Yuzhno-Sakhalinsk, www.sakhalinenergy.ru
Snr. Project Engineer
I’ve had experience in the following Upstream projects:
CAPEX projects at three SakhalinEnergy offshore platforms located in Okhotskoye sea: Molikpaq, LUN-A, PAB, including Planning (1 - 3 level schedules, the latter based on workpacks, for construction) and Scheduling of Project Portflio.
My particular achievement in planning and scheduling is, as a minimum, development of a scheduling tool for Sakhalinenergy Projects Dept., which enabled asset managers to correctly plan construction activities on offshore platforms with given labour resource restrictions. The tool is currently used as I know and appreciated. Also, planning multiple brown-field projects is a great experience for a scheduler\planner, see below my projects.
Overall responsibilities:
Project Engineer for brownfield projects on 3 offshore platforms.
Project delivery from initiation to closeout.
- Project planning/scheduling/budgeting
- project initiation
- scoping work for a design contractor
- project controls
- providing discipline health control via available discipline resources
- procurement initiation, planning and control
- materials&equipment delivery control
- level 2 construction planning
Examples of my small projects:
- various modifications to process piping
- various chemical injection skids/modifications to them
- various heattracing/insulation jobs
- winterization of produced water injection well to prevent water freeze when injection stops for any reason
- automation of manual valves
- installation of filtration skid on heating media system
- replacement and installation of various instrumentation, like flowmeters, pressure gauges/transmitters etc.
- drilling module (shale shakers) HVAC modifications to prevent oil discharge through HVAC outlet
- design/fabricate/install a storage for lube oils
… etc. with total number of projects up to 55 simultaneously executed; most in define/execute phase.
July 2009 — November 2010
1 year 5 months
Jacobs Consultancy BV
Moscow
Oil and Gas... Show more
Project Engineer
Project engineer in consultancy project.
Developing project execution plans (some input in), project calendar schedules, cash flows, control budget, participate in resource planning on early stages of projects (benchmarking statistics provided by Jacobs Consultancy), participate in risk evaluation sessions, interactive calendar planning sessions, schedule control sessions.
For calendar planning used MS Projects, for resource planning used own tool.
The project was:
Upgrade of gasoline/diesel fuel quality, portfolio of projects on three major refineries owned by TNK-BP.
October 2008 — July 2009
10 months
GIPROGAZOOCHISTKA, engineering company.
Moscow
Oil and Gas... Show more
Project Engineer
Project Engineer for Kandym gasfield development project.
Developing Project Execution Plan for Kandym gasfield located in Uzbekistan. Project was executed by Toyo Engineering (concept design, management), TyumenNIPIneft (FEED) and Giprogazoochistka (detail design); with some minor participation of Uzbekistan engineering/construction companies.
Essentially my job was definition and allocation of scopes of work to participants, developing basis of applicable standarts (mixture of Russian and Uzbekiston regulations), high level planning, develop project execution plan.
Project was stopped on early stage due to political/ownership turbulence in Uzbekistan around the project.
July 2007 — September 2008
1 year 3 months
SNC LAVALIN
Russia, www.snclavalin.com
Construction, Real Estate, Architecture... Show more
Project Engineer
SNC Lavalin, engineering company.
Project Engineer for Vankor oilfield development project.
September 2006 — July 2007
11 months
Yuzhno-Sakhalinsk, www.sakhalinenergy.ru
Project Engineer
Project engineer for small brownfield offshore projects on an offshore platform.
Job essentially the same as in 2010 - 2013 with this company, see above.
Short period of employment was for personal reasons
August 2004 — July 2006
2 years
Fluor Daniel subsidiary in Russia.
Moscow
Procurement specialist
Material coordinator/Procurement specialist for
Sakhalin-1 Onshore Process Facilities Project
The job was mostly civil/structural materials coordination. Design was done by a major Russia design company VNIPINEFT, and my task was to ensure all materials from civil/structural drawings ( BOMs as separate document are not done by Russian design companies) are purchased and correctly allocated to construction workpacks. The job was done successfully using my own tool, which was further preferably used by construction team (preferably to Fluor’s MaterialManagement software).
Skills
Skill proficiency levels
About me
1. Engineering degree.
2. 10 years experience in Oil&Gas industry
3. Good knowledge of all project services activities.
4. Practical knowledge of Primavere, MS Project software
5. Good written and oral communication in English.
Higher education
1986
Higher education
Moscow Engineering and Physics Inst / Московский Инженерно-Физический институт
Technical (applied) Physics/ Ф-т Технической Физики, Engineer, Physics of metals
Languages
Professional development, courses
2011
Essentials of project delivery course
Shell, Project delivery critical issues
2011
Primavera for project planning course
Shell, Planning projects with Primavera
2006
Exploration and Production cycle course
Shell, Exploration and Production
1999
Earned value methodology
ABB, Earned value methodology
Citizenship, travel time to work
Citizenship: Russia
Permission to work: Russia
Desired travel time to work: Up to one hour