ETA company
Санкт-Петербург
Строительство, недвижимость, эксплуатация, проектирование... Показать еще
CEO
Electrical, Heating and Automation of residential, public and industrial buildings. The main objects:
1) 2009 "St. Petersburg Metropolitan" Customer: "EnergoMaster" Overhaul Depot lighting system "Neva". Serving as a direct supervisor, analysis and elaboration of project documentation for compliance with Russian standards. Team leadership up to 25 people. Night work associated with the interruption of electric trains underground. Choosing a contractor to perform work on the automation of ventilation and commissioning works.
2) 2009-2011, the automobile plant "Hyundai Motor Manufacturing Rus" temporary power construction site, the current operation of energy facilities, installation of electrical networks and systems in the main body of the plant: power systems, lightning protection system active, electricity metering systems. Total cost of the project more than 50 mln. Rubles. Customer: "Hyundai Emco Rus" and "Hyundai Motor Manufacturing Rus".
Direct supervision of the object in terms of approval of plans runs underground utilities, opening authorization (warrant) on the excavation, preparation of a package of executive documentation, search and implementation of technical solutions for active lightning plant-based equipment Forend. Control of the supply of materials and equipment to the object matching statements replace equipment with the customer counterparts. Monitoring of compliance with rules and regulations of the Russian norms at work.
3) 2011. Installation of electrical networks and systems of plants satellite components suppliers for Automobile Plant "Hyundai Motor Manufacturing Rus". Plants Donghu Rus Rus and Shenyang. Organization of temporary power plant Donghu Rus via DSU. Total cost of the project more than 10 mln. Rubles. Customer: "Hyundai Amco Rus" Ltd. and "Donghu Rus".
Supervision of the object in terms of mounting cable support hardware, installation of cable lines. Select by order of the customer, design, placing an order, delivery and installation of the main switchboard with ATS to 500kVA. Control of the supply of materials and equipment to the object matching statements replace equipment with the customer counterparts. Direct supplier selection and implementation of temporary power plant during construction by means of a sublease diesel generators power 600kVA and 2 pcs for 300 kVA. Organization of fuel supply. Organization and implementation of parallel operation of the Diesel machines. Monitoring of compliance with rules and regulations of the Russian rules and norms at work.
4) 2011. Installation of electrical networks and systems aboveground section of the pipeline Nord Stream area Vyborg LO. Organization of temporary construction camp; installation of metal structures, cables, sensors, lighting systems and perimeter security. The total project cost more than 20 000 euros. General contractor: LLC "Imtech Russland"
Team leadership up to 80 people. Organization mobilizing construction camp for 300 people.
Search and implementation of technical solutions and the grounding of electrical installations in a rocky soils. Monitoring of compliance with rules and regulations of the Russian normsat work.
5) 2011. Reconstruction of electric networks and systems at the plant expansion Ltd. "General Motors Auto" g.Spb. Reconstruction of transformer substation, installation of masts perimeter lighting, installation of low-current communication systems, security and fire alarm systems, power supply systems. Remove the networks from the construction site. Total project cost is 12 million rubles.
Direct supervision of the object in terms of approval of plans runs underground utilities, opening authorization (warrant) on the excavation, preparation of a package of approvals for JSC "Lenenergo" in terms of changes in the composition of consumers of electricity consumed by the plant and change the active power released within the limits of consumption. Contractor selection and implementation bookmarks pipe route KL by horizontal directional drilling under roads. Control of the supply of materials and equipment to the object matching statements replace equipment with the customer counterparts. Monitoring of compliance with rules and regulations of the Russian norms at work.
6) 2010 - 2012 Installation of electrical networks and systems at the facility Mega Computing Centre (DPC) for "Sberbank" in Moscow. The total project cost of more than 1 500 000 EUR. Installation of power boards; supply and installation of cable metal support constructions; busbar mounting; Installation of fire alarm systems. Main Contractor LLC "Mercury".
Direct supervision of the object in terms of mounting cable support hardware, runs of cable lines. Select by order of the customer equipment for the installation of cable lines, low-voltage switchgear. Control of the supply of materials and equipment to the object matching statements replace equipment with the customer counterparts. Monitoring of compliance with rules and regulations of the Russian normsat work. Letting the customer works. Budget evaluation of the project from tender stage to the implementation stage.
7) 2013 Electrical work in the reconstruction GBOU boarding school №576 at St. Petersburg, IN, etc. Kim's house 24. Reconstruction of the main switchboard, network internal power supply and external lighting area. Total project cost is more than 6.5 mln. Rubles. General contractor: OOO "Areal-S"
Direct supervision of the object in terms of mounting cable support hardware, runs of cable lines, all electrical equipment and lighting. Select by order of the customer, design, placing an order, delivery and installation of the main switchboard with ATS to 35kVA.
Addressing the accession of additional electric power to the JSC "Lenenergo". Budget evaluation of the project, directly involved in the adjustment of estimates.
8) 2013-2014 Installation work on the organization of the electricity system and lighting for office and warehouse complex for the needs of SNS-Neva. The total project cost of more than 1.2 million rubles. General Contractor LLC "Arkouda" Direct supervision of the object in the installation of electrical equipment and networks. Monitoring of compliance with rules and regulations of the Russian norms at work.
9) 2013-2014. Conducting research, design and installation of transmission facilities of the Leningrad Regional Electric Grid Company. Major repairs, reconstruction and new construction of hi and low voltage electrical air lines and cables with voltage up to 10kV, Substations, switchgears. The total value of contracts of more than 50 mln. Rubles.
The choice of artists design works, supervision and participation in the coordination of the project with the customer, the district administration, the owners of the adjacent communications, obtaining the act of choice land, manual installation process with the need to disconnect from the network for consumer applications in the electrical network design Permit to Work in existing installations. . Monitoring of compliance with rules and regulations of the Russian norms at work. Acceptance of work from subcontractors.
10) 2011- 2013 - Electrical work at JSC "Mobile Tele system" (MTC) in the region of the North-West. Supply and installation of uninterruptible power supply UPS, upgrade lighting and electricity. The total cost of more than 10 mln. Rubles.
Direct supervision of the object in the installation of electrical equipment and networks. Monitoring of compliance with rules and regulations of the Russian norms at work.
11) 2011-2014. Electrical work for customers: "Gazprom Transgas"; JSC "Russian Railways"; Administration Vasileostrovskij to St. Petersburg and others.
12) in August. 2014. December. 2014. Azimut Hotel Saint-Petersburg. Reconstruction of power supply systems, ventilation and smoke away.
13) September. 2014. - Feb. 2015. Academy of Beauty L'Oreal. St. Petersburg Kamennoostrovsky etc. Etc. 60