Inspector of construction control.
Inspector of construction control.Inspector for welding and civil works. Professional Experience
DUTIES AND RESPOSIBILITIES AS A (Welding Inspector)
1. Responsible for quality control & inspection of piping fabrication activities.
2. Review of WPS, PQR.
3. Witness for Welder Qualifications.
4. Prepare Weld maps.
5. Prepare Inspection reports(Fit-up, Final Visual)
6. Check list Preparation.
7. Co-ordination/Witnessing of all NDT Inspections.
8. Line check, Punch list Preparation, and Hydro test Package Preparation.
9. Prepare Weld maps and As-Built for final document.
10. Preparation & Submittal of QC Dossier and Engineering Document.
DUTIES AND RESPONSIBILITIES AS A (Mechanical Inspector)
1.Line checking and clearing the punch items before the pressure test on completed pipelines.
2.Preparation QA/QC documents, site quality plans, inspection test plans, work procedure, welding procedures etc.,
3.Witness performance and testing of procedure qualification test assemblies, supervise these activities.
4.Perform inspection on erection and installation of prefabricated pipe lines.
5.Checking the piping materials as per codes and process standard specifications.
6.Preparing take of list as per isometric drawing.
7.Inspection of shop fabrication of piping spools and supports. Visual inspection of plant piping and preparing Punch list after installation.
8.Supervise and Quality Assurance on the erection, mounting and alignment activities of rotating equipments.
9.Witness cleaning / installation of equipments prior to installation.
10.Reviewing the approved quality plans, manuals, scope of work to perform the required inspection.
11.Complete responsibility of planning & supervision to the works of piping Supervisor / Foreman, Welders, Pipe fabricators, Fitters, Grinders, Riggers and Crane operators checking of Material take off list.
12.Reviewing the applicable instruments for inspection with valid calibration certificates.
13.Preparation of Hydro test packages as per PID, Isometric drawings, hydrostatic drawings and all related documents.
14.Witnessing Hydro testing.
15.Ensure satisfactory identification of materials, proper protection of piping and fittings. Verify proper size and schedule of pipe, rating of flange face and fittings.
Project: Construction of the 1A section of the Achimov deposits of the Urengoy field for full development with the release of the starting complex (20 wells). Construction of pipelines for collecting and transporting gas from gas wells.
Implementation of technical supervision, control of HSE requirements, and provision of technical support services for the construction of the facilities of section 1A of the Achimov deposits of the Urengoy field for full development with the release of the starting complex (20 wells).
Implementation of quality control on behalf of the customer for the performance of construction and installation works, quality control of mechanical and installation works of the main and technological pipelines, metal structures and reservoirs, cluster wells, electric power transmission lines to the bush of gas wells, gas well construction. Filling of gas wells, construction of roads to them. Control over the availability and correctness of the primary executive documentation (executive schemes, instrumental surveys of assembled structures, engineering communications, general and special work logs), making changes to it in connection with identified shortcomings and defects. Provision of weekly and monthly reporting data on the activities of contractors in the field of HSE, HSE, and forms in accordance with the forms established by the Customer.
Certification of welding procedures. Quality control of welded joints, field and process pipelines. Certification of welding procedures, insulation works. Certification of welders at the admission joints. Certification of welding procedures RAD, RD. Monitoring the cleaning and calibration of the pipeline. Preparation of production and executive documentation, delivery of documentation to the "Customer". Control over the compliance of the accepted and completed work volumes (in the form of KS-2, KS-3, KS-6A) participation in certification commissions, inspection and admission to work of personnel in the production of especially hazardous and special works, participation in commissions on testing and commissioning of facilities Completed construction in operation.