Nova Energies
Superintendent HVAC/MEP
The project provides for the construction of three technological lines for the production of liquefied natural gas (LNG) with a total capacity of 19.8 million tons per year and stable gas condensate up to 1.6 million tons per year.
Key Responsibilities
Manage all aspects of HVAC/MEP construction projects, including scheduling jointly with the subcontractor and quality control.
Coordinate with project manager, engineers related disciplines , and subcontractor to ensure projects are completed on time and to the required specifications.
Supervise and direct construction crews, ensuring that all work is performed safely and efficiently.
Maintain accurate records of project progress and report on project status to senior management.
Communicate regularly with clients to ensure their needs are being met and that they are satisfied with the progress of the project.
November 2020 — May 2022
1 year 7 months
Supervisor and field engineer HVAC
Amursky Gas Processing Plant, stage 4. Gas Processing Plant NGL/NRU and Helium Concentrate Production Unit N1
At the Amur Gas Processing Plant (AGPP) project, at Linde, I carried engineering work on the construction site, as well as service adjustment of the supplied equipment, checking the accuracy of the installed equipment and its performance after all the necessary tests.
My professional duties on the site included:
Daily monitoring of systems installed by the building contractor. Maintenance and control of works on installation of HVAC systems and safety systems (gas extinguishing, foam extinguishing, fire monitor and fire hydrants).
Participation in inspections with representatives of the customer and general contractor for the incoming material and equipment control for compliance with MDR.
Participation in inspections with representatives of the customer and general contractor for the assembling of installed HVAC (heating, ventilation, air conditioning systems), as well as safety systems (gas, foam extinguishing, fire hydrants and fire monitor).
Participation in inspections for pressure tests of heating and air conditioning systems, as well as safety systems (gas, foam extinguishing, fire hydrants and fire monitor).
Participation in inspections with representatives of the customer and general contractor for loop test of measuring and recording apparatus and rotating equipment.
Performing individual tests (measuring vibration and temperature of rotating equipment).
Solving all issues related to manufacturing defects of supplied components for HVAC systems, as well as firefighting systems. Improvement of the term of re-delivery of defective equipment or materials required for construction and installation work.
Implementation of reports requested by general contractor, in accordance with contractual obligations.
Together with venders, checking the ModBus RTU Protocol and its performance.
Answers to TQ (technical query)
Answers to OSD (Overage shortage and deviation report).
Answers to NCR (Non-Conformity report).
If discrepancies were identified, NCR were sent towards general contractor or supplier.
Answers to NCR sent by general contractor.
Business correspondence and meetings with representatives of suppliers, general contractor and designers.
April 2020 — November 2020
8 months
Tecnimont
Omsk
Supervisor HVaC
Currently I am working at a large oil refinery in Siberia GazpromNeft in the city of Omsk, employed by EP + Cm contractor which is named by Tecnimont
I am responsible for below mentioned activities :
Attending Daily inspections
To Control Main contractors activities , to maintain quality and implementation of HVAC systems (according to SP and GOST standards)
To arrange Necessary Coordination with suppliers of equipments and materials, control arrival of material accordingly agreed manufacturing schedules
To check specifications in advance and in case required to requests for material which is missing
Conducting open package inspections on the site with signing RF
Signing of acts in accordance with the norms of the Russian Federation (NOSTROY register s-71-211424)
Participation in meetings and walk around with the client and the general contractor
Preparation and issue of weekly HVAC progress reports for Gazpromneft.
To work with working documentation and amendments in accordance with the company's regulations and the norms of the Russian Federation.
Verification of as-built documentation and performed works according to working documentation.
I have computer knowledge which consist Autocad , office programs and Nawisworks
In case required accordingly working conditions make overtime .
I have high communications skills with colleagues
September 2018 — November 2019
1 year 3 months
PIZZAROTTI
Supervisor HVAC
Pizzarotti is a large Italian construction company.
My professional duties included: daily monitoring of the operation of mounted engineering systems on site. Quantity manpower and engineers required for installation systems. Quality control of work performed.
Ensure safe, correct and uninterrupted work, control the supply of materials for HVAC systems as well. Monitoring and controlling subcontractors on site. Reports to the mechanical superintendent, scheduling, organization of production meetings.
Verification of availability at a Fabrication Contractor of a reliable plan and resources to accomplish works on prefabrication of components, on-site fabrication, testing.
Supervision and reporting within the discipline framework.
Supervision of contractor’s work within a relevant discipline. Hand over to the client installed systems.
Control over fire and technical safety on the site. Work with field design and fabrication teams to verify and approve all Contractor’s work results. Enforcement of compliance with specifications, standards and schedules.
Identification and highlighting of all possible risks, opportunities or threats that may positively or negatively impact quality or project tasks. Verification and signing as-built documentation.
January 2018 — September 2018
9 months
South Tambey LNG Russian branch
Supervisor HVAC
South Tambey LNG is the general contractor for the Yamal LNG project. The company is a joint venture of such international companies as Chiyoda, JGC and Technip.
Ensure safe, proper and smooth execution of both modular and stick-built HVAC system on site
Monitor and supervise subcontractors on site
Reports to Mechanical Superintendent
Ensure that HVAC works are carried out in accordance with the STL safety practice and standard and approved method statements
December 2015 — December 2017
2 years 1 month
Codest international S.R.L
Construction, Real Estate, Architecture... Show more
Supervisor HVAC
Project location: subway Dinamo, Hotel Hyatt Regency Moscow Petrovsky Park and apartments
Technical Supervision Engineer (Heating, Ventilation and Air Conditioning; Water supply, fire fighting and Sewerage)
Carried out technical supervision on construction and assembly works on site (heating, ventilation and air conditioning; water and sewerage lines).
Monitored service scopes and material quality.
Monitored the compliance of the performed works with the Detailed Design and regulatory instruments (Construction Rules and Regulations (SNiP), Design and Construction Specifications (SP), State Standards (GOST)).
Accepted the completed works.
Monitored the construction activity schedule.
Wrote business letters.
Checked contractors’ documents on site.
Received and checked the incoming materials and equipment.
September 2013 — May 2016
2 years 9 months
Trest Moselektrotyagstroy CJSC
Moscow, tmets.ru/
Construction, Real Estate, Architecture... Show more
Supervisor HVAC
Technical Engineer MEP systems
Managed construction services at thesite.
Drafted requests for materials.
Engaged contractors for assembly works.
Monitored the quality of assembly services according to Construction Standards (SP).
Confident working documentation handling (signed up acts, accepted scope of works, etc.)
Dealt with suppliers.
Drafted activity schedules.
Supervised professional construction teams.
Solid awareness of modern engineering systems and materials.
Independence. Confidence. Responsibility.
January 2012 — January 2013
1 year 1 month
Zarubezhvodstroy OJSC
Construction, Real Estate, Architecture... Show more
Construction Engineer
Project in the Republic of the Niger
Construction Engineer
Construction of KANDADJI Water Power Plant, the River of Niger, the Republic of the Niger.
1. Provided construction and installation services on site (township for customer and contractor; industrial facility)
2. Provided earthwork activities (constructing trenches, pits for residential house foundations, grinding and sorting facility, concrete unit, etc.)
3. Provided quality control over materials to be used.
4. Monitored the compliance with construction activity schedule and regulatory instruments
5. Kept work logs, acts, M29
6. Provided assembly works in accordance with the Detailed Design.
7. Operated survey tools (level).
8. Managed construction team (30-140 persons).
9. Supervised the compliance with the occupational safety standards.
June 2010 — April 2011
11 months
Intertechproject OJSC under Russian Legislation
Construction, Real Estate, Architecture... Show more
Supervisor HVAC
Technical Engineer MEP systems
Project: Provide installation and assembly of internal sewerage, water supply and heating systems on Business Center located at: 22-24, Ozerkovskaya nab., Moscow (total area: 80,000 m²)
Supervised the activities of the subcontractors.
Kept data logs, acts and information documents
Purchased materials and provided quality control over them.
Cooperated with the design unit.
Approved materials and equipment applied with the Customer.
Arranged and held weekly meetings with the subcontractors.
June 2009 — February 2010
9 months
Alvar Group LLC under Russian Legislation
Construction, Real Estate, Architecture... Show more
Technical Engineer HVaC systems (Sanitary Engineering Specialist)
Provided assembly services and managed construction works.
May 2005 — November 2008
3 years 7 months
Mosgorgydrostroy LLC under Russian Legislation
Construction, Real Estate, Architecture... Show more
Supervisor HVAC
Installed heating, ventilation and air conditioning utility systems at civil facilities (6 residential facilities and 3 day-care facilities in Zelenograd, Moscow, Khimky (Kurkino district).
Provided quality control and the compliance of assembly services with Project Design Documentation according to Construction Rules and Regulations (SNiP).
Kept work logs.
Cooperated with representatives of Customer.
Commissioned facilities.
Provided quality control over incoming materials to be used.
Managed construction teams (40 persons).
November 2004 — April 2005
6 months
Gornospetsstroy LLC under Russian Legislation
Construction, Real Estate, Architecture... Show more
Construction and Assembly Specialist
Provided construction and assembly services at residential facility site (Kurkino district, Khimky)
Provided earthwork operations (constructing pit for residential facility foundation)
Provided quality control over the incoming materials to be used
Supervised construction activity schedule and compliance with regulatory documents
Kept work logs.
Provided in-situ works in compliance with Detailed Design
Operated survey tools (levelling box)
Managed construction teams (20-30 persons)
Supervised the compliance with operational safety
July 2004 — November 2004
5 months
Don Assembly Department of Novomoskovskkhimstroy LLC under Russian Legislation
Construction, Real Estate, Architecture... Show more
Construction and Assembly Specialist
Construction and Assembly Specialist
Provided construction and assembly works at Tula Chermet Facility
Provided earthwork operations (constructing pit for industrial facility foundation)
Provided quality control over the incoming materials to be used
Monitored construction activity schedule and requirements of regulatory documents
Kept work logs.
Assembled metal structures (welding column segments and frameworks)
Operated survey tools (leveling box, theodolite)
Managed construction teams (10-15 persons)
Driving experience
Own car
Driver's license category BAbout me
Project Design Documentation: confident user
Regulatory documentation (Construction Rules and Regulations (SNiP), Design and Construction Specification (SP): solid knowledge
PC: confident user
Family status: married
Children: no
Private car: yes
Open to business trip: yes
Higher education (bachelor)
2018
Higher education (bachelor)
Moscow Institute of Technology, Moscow
Industrial and civil engineering, Civil engineer
2003
Higher education (bachelor)
Novomoskovsk Construction College
Industrial and civil engineering, Construction technician
Languages
Professional development, courses
2020
Organization of construction, reconstruction, overhaul of capital construction projects
Nostroy c-71-211424
Citizenship, travel time to work
Citizenship: Russia
Permission to work: Russia
Desired travel time to work: Doesn't matter